  Project tasks

Purpose

The purpose of this phase is to complete the cut-over and go-live. In addition, the project is to be handed over to the customer and support has to be initialized.

Procedure

The following lists the tasks that have to be completed during this implementation phase:

 

Task #

Description

Results

Est. duration

Team members

1

Production support

 

22 hours

 

1-1

Provide on-site support during initial go-live

- SAP Business One consultant on-site to immediately respond to any issues

20 hours

SAP Business One consultants, SAP Business One project manager, client IT administrator

1-2

Resolve outstanding critical business or technical issues

- All critical outstanding issues are resolved

N/A

Client IT administrator, client functional leads, SAP Business One consultants

1-3

Handover support and system administration to client team

- Client team has taken over support and system administration
- Go-Live checklist in PartnerEdge Portal has been completed to activate support

2 hours

Client IT administrator, client project manager, SAP Business One consultants

2

Project closing

 

2 hours

 

2-1

Conduct project closing meeting

- Project plan reviewed
- All milestones completed successfully
- “Review and Optimization Conferencescheduled
- Customer has signed final project acceptance

2 hours

Project team (see 5.2)

3

Continuous improvement

 

4 hours

 

3-1

Monitor system

- All issues are recorded
- Enhancements to performance, functionality, usability, etc are recorded

N/A

Client IT administrator, client project manager, client functional leads

3-2

ConductReview and Optimization Conference

- “Review and Optimization Conferencecompleted
- Post Go-Live checklist completed

4 hours

Project team (see 5.2)

 

 